MEZ LLC “POTOKY”
Project: Supply of equipment and installation of the boiler room, 2nd phase.
Fuel: Sunflower husks and husk pellets
Equipment: Burner PVG (a)–3500, 12 MWt
Project: Supply of equipment and Installation of the production boiler room of the oil extraction plant based on three KE 25/24 boilers
Fuel: Sunflower husk, coal
Equipment: Burner PVG (a)-3500 15 MWt, generator TLK 18
Project: Supply of boiler room equipment
Fuel: Pellet
Equipment: Boilers KE-4 Burner PV (a)-3500 3.5 MWt – 2 pcs
Project: Supply of boiler room equipment
Fuel: Pellet
Equipment: Boiler KE-25 Burner PVG (a)–3500 12 MWt
Project: Supply of economizer blocks for the E-35-40-440D boiler
Fuel: Sunflower husks, agricultural crop cleaning waste
Equipment: 2 p.
Project: Supply of steam boiler KE-25.0-1.4
Fuel: Peleta, alcohol bard
Equipment: Boiler KE-25.0-1.4
Project: Supply of PVG(a)-3500 8.0 MW burner and boiler room components
Fuel: Pellet, alcohol bard
Equipment: Burner PVG (a)-3500 8 MWt
Project: Development of a steam boiler room Boiler KE-10-14 Thermal capacity 6.0 MW. Steam productivity 8 t/h.
Fuel: Sunflower husks is granular
Equipment: Boiler KE-10-14-370. Burner PVG -6 MWt
Project: Supply, chief installation and commissioning of boiler equipment of 8 MW. Swirl burner 6 MWt
Fuel: Sunflower husk is granulated, bard is alcoholic
Equipment: Burner PVG (a)-3500 16.0 MWt